|
Online edition of India's National Newspaper Wednesday, November 22, 2000 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Classifieds |
Employment |
Index |
Home |
|
Opinion
| Previous
| Next
The NBA, the court and the SSP
By A. Vaidyanathan
THE SUPREME Court verdict in the Sardar Sarovar case has
understandably disappointed the Narmada Bachao Andolan (NBA) and
those who support its stand. Many (like myself) who do not
subscribe entirely to the NBA viewpoint also feel disappointed at
the court's rejection of the plea for an impartial review of the
project as currently conceived, allowing resumption of
construction to raise the dam height to 90 metres and granting
contingent permission for increasing it even further as per the
Governments' plan, subject to weak and fuzzy conditions on
rehabilitation of displaced persons.
The NBA and Ms. Medha Patkar have made a truly praiseworthy
contribution, focussing attention on several important issues
relating to the Sardar Sarovar Project (SSP), and by extension,
to all largescale development schemes. However, the NBA's stance
and strategy in respect of some key aspects call for comment.
The early phases of the movement, predating the NBA, saw a well-
documented and wide-ranging critique of several features of the
SSP. The consequences of submergence of vast areas especially for
the number of people likely to be displaced, the adequacy and
fairness of measures to rehabilitate them and serious doubts
about their implementation figured prominently in the debates. At
the same time, they also raised questions about the rationale of
the project, the assumptions about water availability, economic
viability and problems of financing the huge investment.
However, over time, the NBA narrowed the focus of its protests to
the issues of environment and displacement. It took the position
that large dams were unnecessary and that their adverse
consequences for environment, displaced people and sustainability
far outweighed their benefits.
The NBA's media campaigns and public protests evoked sympathy and
support both within and outside the country. But the Governments
of India and of Gujarat refused to even discuss, much less set up
a credible forum to examine independently and on merit, the
issues raised by the NBA and several other critics. The issue was
then taken to the Supreme Court. The petition challenged the
basis on which the project was given technical, economic and
environmental clearances, pointed to serious lacunae (in terms of
transparency and objectivity) in the mechanisms and procedures
for making these decisions, and documented the defects and
inadequacy of the proposed rehabilitation measures and the lack
of any credible mechanism for remedying these defects and
ensuring effective implementation.
However, the NBA's argument that large dams are not necessary to
increase production and that their contribution (indeed the
contribution of irrigation generally) to increased production is
meagre is questionable. In fact, on an average, a hectare of
irrigated land produces three to four times as much as a hectare
of rainfed land. And practically the entire increase in
production in recent decades has come from an expansion of
irrigated area and rising yield from irrigated lands; there is
hardly any increase in the yield from rainfed lands.
Given our climate, the possibility of substantially increasing
crop yields and more intensive cropping depends crucially on
augmenting water supply from local rainfall and making it
available for a longer period and with greater assurance. This
cannot be done unless surplus rainfall in the rainy season, and
in areas with high rainfall, is stored for use in the dry seasons
and regions. One can readily agree that much more attention
should be given to a more effective use of local rainfall through
integrated watershed development; and that more should be done to
improve and extend tanks, ``bhandaras,'' diversion of local
streams and such smallscale, so-called minor irrigation works.
But these can go only a limited way. The total capacity of all
minor surface works in the early 1950s is estimated at 15 billion
cubic metres (BCM) and that of large storages, about 18 BCM.
Since then we have added more than 200 BCM, all from large
storages. While certainly there is scope for extending and
improving small works, they cannot provide a storage of this
magnitude. Sizable surface and underground storages cannot be
avoided. They should not be seen as alternatives; we should
instead look at ways in which large and small storages, surface
water and ground water could be combined so that the requirement
of large storage is minimised and water is used more carefully
and effectively.
Many things are wrong, and seriously wrong, with the way
irrigation works have been designed, constructed and managed:
poor project preparation, excessive preoccupation with large new
projects, inordinate delays and high costs, corruption, poor
management and inequitable distribution of costs and benefits.
The NBA had an excellent opportunity to focus on these issues in
the context of the SSP. Important questions on costs, patterns of
water use, productivity impact and regional distribution of
benefits were in fact raised early on. This stimulated interest
not only among the public at large but also professionals outside
the Government. At least one group which included engineers and
social scientists with extensive experience in irrigation
management produced a well-researched and reasoned alternative to
the official plan.
This proposal argued that lowering the maximum height of the dam
would drastically reduce the extent of submergence and the number
of people displaced. The storage of the Sardar Sarovar would be
smaller, but the total water utilisation as envisaged in the
official plan could be ensured by using the existing tanks in
Saurashtra to store part of the water and operating them in an
integrated way. Moreover, this group argued for different
patterns of water allocation among regions and crops to ensure a
more productive and sustainable use of water and more equitable
sharing of benefits. It is regrettable that the NBA did not
consider this alternative seriously. At any rate it chose not to
use it to press the Government and later the court for reviewing
the project and instead argued for its outright rejection.
However, this alternative was brought to the court's notice in
other submissions.
Nevertheless, the court evidently was not persuaded of the
justification for ruling in favour of a review of alternative
designs. This prima facie is somewhat surprising. One would have
thought that a solution which could drastically reduce
displacement and ensure a more effective use of available
supplies deserved serious consideration. Given the complexity of
the problem, the court may not be in a position to assess the
merits of alternatives. But it could have recommended an
independent expert review of the proposed options. That would
have helped to create a much-needed and credible mechanism for
addressing the legitimate concerns of the affected parties and
finding a reasonable and fair compromise between conflicting
interests.
The other issue which the judgment has not resolved is the
question of compensation. There are several aspects: (a) the
basis for determining those eligible, (b) the criteria for
deciding the magnitude and form of compensation and (c)
mechanisms to ensure that the claims are in fact settled fully
and speedily. Without these no package can be complete. The
verdict leaves the criteria by which to judge whether or not the
rehabilitation package is satisfactory ill-defined; and the
mechanisms to ensure implementation even more so.
There is also the question who should bear the cost of
compensating the displaced. Placing the responsibility entirely
on the State is neither prudent nor fair. The current policy of
the State bearing the full responsibility for financing
investment costs and of pricing water far below the costs of
providing it has resulted in a huge and mounting burden on
budgets. In this context, making the beneficiaries of the project
liable to compensate those who are displaced by it merits serious
consideration. The judgment, however, does not go into the
substantial issues relating to compensation and lay down at least
the principles on which they should be settled.
Altogether one is left feeling that the court missed a good
opportunity to give an impetus to the much-needed reform for
ensuring transparency and accountability in the way large public
projects are handled and credible mechanisms to address and
accommodate the concerns of those adversely affected in a fair,
humane and equitable manner.
(The writer is Professor Emeritus, Madras Insititute for
Development Studies.)
Send this article to Friends by E-Mail
|
|
Section : Opinion Previous : A litmus test for disinvestment Next : ASEAN in turmoil | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Classifieds |
Employment |
Index |
Home | |
|
Copyrights © 2000 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|