|
Online edition of India's National Newspaper Wednesday, December 20, 2000 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Classifieds |
Employment |
Index |
Home |
|
Southern States
| Previous
| Next
Idukki dams under serious risk of failure
By Roy Mathew
THIRUVANANTHAPURAM, DEC. 19. The dams of Idukki project are
facing serious risks of failure on account of a variety of
factors.
These include the precarious condition of the Mullaperiyar dam
upstream, the inadequacy of the spillways, slope instability in
the catchment areas, siltation, earthquakes and lack of proper
instrumentation to monitor the Mullaperiyar, Idukki, Cheruthoni
and Kulamavu dams.
Tamil Nadu has long been arguing that the Mullaperiyar dam could
withstand a water level of 145 feet or higher. However, experts
from Kerala dispute this. Last week, experts from both Kerala and
the Centre came across fissures and leaks in the dam body. A
report of the Central Soil and Materials Research Station is
expected to be submitted in a week's time.
The dam was constructed at a time when hardly any official
regulations or codes of practice in construction existed. Effects
of uplift force and seismicity were not considered in the design.
No drainage gallery had been provided, as in modern dams, to
release pressure. The dam was constructed as one long continuous
block using rubble masonry and lime surkhi mortar and without
providing construction joints.
According to engineer, Mr. M. K. Parameswaran Nair, who is
representing Kerala in the Committee set up by the Central Water
Commission to study the issue, the strengthening works undertaken
by the Tamil Nadu Government to ensure the safety of the
Mullaperiyar dam were not adequate. Mullaperiyar had a history of
sweating and leakage from the time of its commissioning. In the
1930s and the 1960s, the Government had resorted to large-scale
grouting and guniting.
The total cement used for this was 542 tonnes. According to Tamil
Nadu's own figures, the annual leaching noticed was of 30.488
tonnes a year.
So, it was clear that more cement than that used for grouting has
leached out, leaving holes in the dam body. Moreover, there was
no guarantee that the entire hollow space inside the dam had been
filled up during the grouting.
Mr. Parameswaran says that though Tamil Nadu had given a concrete
backing on the rear face as part of strengthening measures, this
was not fully integrated with the old structure. There was a gap
between the old and new structures and hence the whole would not
be acting as a monolith.
Tamil Nadu's claim that the dam was strong was based on the
assumption that the hybrid structure is a monolith. Though
drainage galleries were provided through the new structure, these
had become ineffective through clogging.
So, there was no mechanism to release pressure developing in the
foundation. Considering all this, the failure of the Mullaperiyar
dam in a heavy flood was a distinct possibility.
Dams are designed to handle the biggest probable flood that can
occur any time in 1,000 years. Each dam has a probable maximum
flood (PMF) estimated for its design. In the case of Idukki
project, the probable maximum flood is 8,000 cumecs. The dams and
spillways are designed to handle an inflow of 5,100 cubic metres
per second.
The balance flood was to be absorbed by the capacity available
between Full Reservoir Level (FRL) and the permissible Maximum
Water Level.
The PMF incorporated into the design of Mullaperiyar was 2,495
cumecs. Idukki was designed on the assumption that the maximum
flood discharge from Mullaperiyar would be only 2,495. However,
the PMF of Mullaperiyar basin was revised as 6,003 cumecs as per
the recommendations of the Central Water Commission. The Idukki
project, according to Mr. Nair, would not be able to handle such
an inflow if the Idukki reservoir is at FRL or near to it.
The chances of both the projects getting caught in a probable
maximum flood situation simultaneously are high considering the
fact that their catchments are similar and adjacent.
This means that even the normal operations of the Mullaperiyar
dam at full reservoir level of 152 feet (during monsoons) would
be at a heavy risk to Idukki, not to speak of a failure of the
Mullaperiyar dam.
The situation calls for urgent construction of additional
spillways at Idukki reservoir. Otherwise, the reservoir levels
would have to be kept down. The situation is compounded by the
fact that the Idukki's own estimated PMF needs revision.
After Idukki dams were built, several smaller rivers had been
diverted into the reservoir to augment the availability of water.
This would have raised the PMF.
At anytime, a failure of the Mullaperiyar dam could be
catastrophic for Idukki. The project, built to hold 2,000 million
cubic metres of water, will have to cope with a sudden inflow of
up to 443 million cubic metres of water from 50 km away. Hundreds
of towns and villages in three districts of the State would be
wiped out if the dams of Idukki fail.
Even in its normal operation, earthquakes, siltation and
instability of slopes in the catchment area pose some risks.
Idukki dam is designed to withstand a horizontal acceleration of
0.05g. and vertical acceleration of 0.025g. This means that it
can withstand earthquakes bigger than those reported from the
area now.
However, it is to be noted that even smaller dams, like the Lower
Periyar, were now designed to withstand horizontal acceleration
of 0.1g. However, landslides in the catchment area can cause dam
failure as the reservoir could overflow if large masses of earth
falls into it.
Studies by the Department of Geology of the University of Kerala
and the Centre for Earth Science Studies have shown that many
slopes in Idukki district, including those in the catchment are
unstable. Recent studies have also indicated that the reservoir
is silting up heavily, reducing its storage capacity.
The technical committee constituted by the State Government has
found that the Mullaperiyar dam had some instrumentation only in
the backing concrete portion. These were four uplift pressure
cells, four strain metre groups with no stress strain metre, four
joint metres and eight thermometres. Set up sometime in the
eighties, these instruments were either not functional or not
being systematically monitored. The Committee observed that the
instrumentation was neither effective nor the monitoring
systematic.
The monitored data are seldom interpreted.
The situation with respect to the dams of Idukki project are also
not much different. Most of the embedded instruments are not
functioning and data from other instruments are not being
interpreted properly.
In a presentation at the Institute of Engineers here a few years
back, retired engineer of the Board, Mr. M. Sasidharan, had
pointed out the Board was unable to calculate the real stress
pattern existing in the dam.
Malfunctioning of instruments and abnormal seepage had been
noticed. Abnormal press development in foundation drains had also
been detected. In many areas, total neglect, incompetence and
inaction were occurring. Mr. Sasidharan, when contacted on
Tuesday, said that the situation was no different now.
Send this article to Friends by E-Mail
|
|
Section : Southern States Previous : 'A celluloid message against violence' Next : Cong.(I) 'committed' to ties with AIADMK | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Miscellaneous |
Classifieds |
Employment |
Index |
Home | |
|
Copyrights © 2000 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|